Hi all,

I still have faith in Eden Gardens. The project has been delayed due to many factors:

1) Sports City changing from Leasehold to Freehold
2) Dubai Municipality taking over from Dubai Sports City and enforcing new regulations
3) Delay in handover of plot from DSC. They got the plot in May 2007.
4) Dubai Municipality changed the design and insisted on adding a above the ground parking area. The main design was not changed but parking floors were added

This caused the developers alot of delays that were unexpected. I heard alot of developers ran into the same delays.

I have spoken to Jean at their office and she was extremely helpful and changed my payment plan favorably. The new projected delivery date is March 2010 and they are pushing hard for that date

As for their project in IC, it is called Lady Ratan Manor and was handed over this month

Cheers
Daf

Daf

Is there any other general changes that we might expect due to the overtake of Dubai municipality in dubai sports city?
Is the green city regulation / requirements going to be adopted in dubai sports city ,which is recently approved by H H sheikh muhammad bin rashid ?

Do Other members have Any idea / info on this ?